Kinetic Electrical Hawkes Bay was engaged by Brian Perry Civil to carry out this enabling works.
The project involved relocation of the mains cable and earthing system to enable piling works. This critical changeover also involved substantial preparation and planning as the plant provides Auckland’s water supply.
Duration – three months
Staff Number Involved – five
Challenges – maintaining a fully operational plant whilst undertaking project work
Undertaken By – Kinetic Electrical Hawke’s Bay