Kinetic Electrical Hawkes Bay was engaged by HEB Construction to undertake the greenfield construction of the Gisborne Wastewater Treatment Plant ($21 million). It was completed in 12 months. The project included full electrical to site including MCC and PLC. We are proud to have partnered with Schneider Electric for this project to deliver a true turnkey solution for the Gisborne District Council.
Duration – 12 months
Staff Number Involved – ten
Challenges – completion timeline
Undertaken By – Kinetic Electrical Hawkes Bay