The Kinetic Electrical scope of work was the supply, installation and commissioning of process equipment modifications and additions to the existing primary wastewater treatment plant and a new secondary wastewater treatment plant.
Kinetic Electrical Hawkes Bay project managed the installation of new plant and plant modifications.
Duration – seven months
Staff Number Involved – eight
Challenges – installing and integrating new plant into an existing treatment process while maintaining an operational wastewater treatment plant
Undertaken By – Kinetic Electrical Hawke’s Bay